Past Sewer Lines

 McAlpine Creek Relief Sewer, Joint Venture with BRS, Inc.                      $ 17,437,596.00

                                                                           Scope: 8,300 lf 78” Pipe; Creek Crossings, Tunnels, 19 ea 10’ Dia MH

Owner:  Charlotte Mecklenburg Utilities

     Charlotte, NC,  Arnold Jarrell, P.E.  704-399-2551

Engineer:  McKim & Creed, Chuck Shue, P.E. 704-841-2588

Date of Completion:  9/30/10

Contract Time:  700 days




Rocky River Sanitary Sewer Outfall Ph 3                                          $ 1,631,545.21

     1,440 lf 18” PVC & DIP, 30 MH and related appurtenancesScope:  6,323 lf  30” PVC & DIP, 2454 lf 24” PVC & DIP

Owner:  Charlotte Mecklenburg Utilities, Chuck Bliss, P.E. 704-399-2551

Engineer:  McKim & Creed, Chuck Shue, P.E., 704-841-2588

Date of Completion:  2/09/08

Contract Time: 180 days

Contract Completion Time:  180 days


    Sugar Creek Outfall Repair                                                                $ 1,460,049.88

Scope:  242 lf 54” Sewer Pipe; 111 lf 48” Sewer Pipe; Slip-lined 520 lf              

 66” Sewer Pipe; MH; By-Pass And related appurtenances

                        Owner:  Charlotte-Mecklenburg Utility Dept.

                        Contact:  Kit Eller, 704-399-2551

                        Date of Completion:  February, 2014

                        Duration:  200 days

                        Engineer: Parsons Brinkerhoff, Sid Riddick, 121 West Trade Street. Suite       

                             1950, Charlotte, NC  28202, 704-506-7759 

    High Shoals Sewer Interconnect Section 3 – Contract 2.4                 $ 1,744,718.47

                        Scope: 2,582 lf 4” Force Main; 3,187 lf 6” Force Main, 6,350 lf 8” Gravity

                        Sewer; 3,588 lf 10” Gravity Sewer; 7,552 lf 15” Gravity Sewer;

                        62 Manholes: Horizontal Bores and related appurtenances

                        Owner:  Gaston County, NC

                        Contact:  Dan Ziehm, P.E.  704-862-6795

                        Date of Completion: September, 2012

                        Duration:  360 days

                        Engineer:  HDR Engineering, Inc. of the Carolinas, 

    440 South Church Street, Suite 1000, Charlotte, NC  28202  704-377-4182

           

             South Carolina Hwy 51 Gravity Sewer Project – PH 1                         $ 1,133,381.17

                        Scope:  4,741 lf 8”, 12”, 15” Sewer Pipe; 12 ea Manholes; Horizontal

                        Bores, Connections, By-passes and related appurtenances

                        Owner:  York County, SC

                        Contact:  Rick Center, P.E.,  803-684-8571

                        Date of Completion:  February, 2013

                        Duration:  150 days

                        Engineer:  ESP Associates, P.A., 3475 Lakemont Blvd., Fort Mill, SC

    Matt Reiking, P.E  803-802-2440. 